Friday, January 23, 2015

Pipeline Hot Tap

Hot Taps or Hot Tapping is the ability to safely tie into a pressurized system, by drilling or cutting, while it is on stream and under pressure.
Typical connections consist:
  • Tapping fittings like Weldolet®, Reinforced Branch or Split Tee. Split Tees often to be used as branch and main pipe has the same diameters.
  • Isolation valve like Gate or Ball valve.
  • Hot tapping machine which includes the cutter, and housing.
Mechanical fittings may be used for making hot taps on pipelines and mains provided they are designed for the operating pressure of the pipeline or main, and are suitable for the purpose.
  • Design: ASME B31.1, B31.3, ASME B31.4 & B31.8, ASME Sec. VIII Div.1 & 2
  • Fabrication: ASME Sec. VIII Div.1
  • Welding: ASME Sec. IX
  • NDT: ASME Sec. V
There are many reasons to made a Hot Tap. While is preferred to install nozzles during a turnaround, installing a nozzle with equipment in operation is sometimes advantageous, especially if it averts a costly shut down.
Hot Tap set up

Remarks before made a Hot Tap

  • A hot tap shall not be considered a routine procedure, but shall be used only when there is no practical alternative.
  • Hot Taps shall be installed by trained and experienced crews.
  • It should be noted that hot tapping of sour gas lines presents special health and metallurgical concerns and shall be done only to written operating company approved plans.
  • For each hottap shall be ensured that the pipe that is drilled or sawed has sufficient wall thickness, which can be measured with ultrasonic thickness gauges. The existing pipe wall thickness (actual) needs to be at least equal to the required thickness for pressure plus a reasonable thickness allowance for welding. If the actual thickness is barely more than that required for pressure, then loss of containment at the weld pool is a risk.
  • Welding on in-service pipelines requires weld procedure development and qualification, as well as a highly trained workforce to ensure integrity of welds when pipelines are operating at full pressure and under full flow conditions.
Hot Tap fittings

Hot Tap setup

For a hot tap, there are three key components necessary to safely drill into a pipe; the fitting, the valve, and the hot tap machine. The fitting is attached to the pipe, mostly by welding.
In many cases, the fitting is a Weldolet® where a flange is welded, or a split tee with a flanged outlet (see image above).
Onto this fitting, a valve is attached, and the hot tap machine is attached to the valve (see images on the right). For hot taps, new Stud Bolts, gaskets and a new valve should always be used when that components will become part of the permanent facilities and equipment.
The fitting/valve combination, is attached to the pipe, and is normally pressure tested. The pressure test is very important, so as to make sure that there are no structural problems with the fitting, and so that there are no leaks in the welds.
The hot tap cutter, is a specialized type of hole saw, with a pilot bit in the middle, mounted inside of a hot tap adapter housing.
The hot tap cutter is attached to a cutter holder, with the pilot bit, and is attached to the working end of the hot tap machine, so that it fits into the inside of the tapping adapter.
The tapping adapter will contain the pressure of the pipe system, while the pipe is being cut, it houses the cutter, and cutter holder, and bolts to the valve.

Hot Tap operation

Split Tee in practice
Split Tee (www.armorplateonline.com)
The Hot Tap is made in one continuous process, the machine is started, and the cut continues, until the cutter passes through the pipe wall, resulting in the removal of a section of pipe, known as the "coupon".
The coupon is normally retained on one or more u-wires, which are attached to the pilot bit. Once the cutter has cut through the pipe, the hot tap machine is stopped, the cutter is retracted into the hot tap adapter, and the valve is closed.
Pressure is bled off from the inside of the Tapping Adapter, so that the hot tap machine can be removed from the line. The machine is removed from the line, and the new service is established.

Hot Tap Coupon

The Coupon, is the section of pipe that is removed, to establish service. It is very highly desirable to "retain" the coupon, and remove it from the pipe, and in the vast majority of hot taps, this is the case.
Please note, short of not performing the hot tap, there is no way to absolutely guarantee that the coupon will not be "dropped".
Coupon retention is mostly the "job" of the u-wires. These are wires which run through the pilot bit, and are cut and bent, so that they can fold back against the bit, into a relief area milled into the bit, and then fold out, when the pilot bit has cut through the pipe.
In almost all cases, multiple u-wires are used, to act as insurance against losing the coupon.

Line Stopping

Line Stops, sometimes called Stopples (Stopple® is a trademark of TD Williamson Company) start with a hot tap, but are intended to stop the flow in the pipe.
Line Stops are of necessity, somewhat more complicated than normal hot taps, but they start out in much the same way. A fitting is attached to the pipe, a hot tap is performed as previously detailed. Once the hot tap has been completed, the valve is closed, then another machine, known as a line stop actuator is installed on the pipe.
The line stop actuator is used to insert a plugging head into the pipe, the most common type being a pivot head mechanism. Line stops are used to replace Valves, fittings and other equipment. Once the job is done, pressure is equalized, and the line stop head is removed.
The Line Stop Fitting has a specially modified flange, which includes a special plug, that allows for removal of the valve. There are several different designs for these flanges, but they all work pretty much the same, the plug is inserted into the flange through the valve, it is securely locked in place, with the result that the pressure can be bled off of the housing and valve, the valve can then be removed, and the flange blinded off.

Line Stop setup

The Line Stop Setup includes the hot tap machine, plus an additional piece of equipment, a line stop actuator. The Line Stop Actuator can be either mechanical (screw type), or hydraulic, it is used, to place the line stop head into the line, therefore stopping the flow in the line.
The Line Stop Actuator is bolted to a Line Stop Housing, which has to be long enough to include the line stop head (pivot head, or folding head), so that the Line Stop Actuator, and Housing, can be bolted to the line stop valve.
Line stops often utilize special Valves, called Sandwich Valves.
Line Stops are normally performed through rental Valves, owned by the service company who performs the work, once the work is completed, the fitting will remain on the pipe, but the valve and all other equipment is removed.

Line Stop operation

A Line Stop starts out the same way as does a Hot Tap, but a larger cutter is used,.
The larger hole in the pipe, allows the line stop head to fit into the pipe.
Once the cut is made, the valve is closed the hot tap machine is removed from the line, and a line stop actuator is bolted into place.
New gaskets are always to be used for every setup, but "used" studs and nuts are often used, because this operation is a temporary operation, the valve, machine, and actuator are removed at the end of the job.
New studs, nuts, and gaskets should be used on the final completion, when a blind flange is installed outside of the completion plug.
The line stop actuator is operated, to push the plugging head (line stop head), down, into the pipe, the common pivot head, will pivot in the direction of the flow, and form a stop, thus stopping the flow in the pipe.

Completion Plug

In order to remove the valve used for line stop operations, a completion plug is set into the line stop fitting flange (Completion Flange).
There are several different types of completion flange/plug sets, but they all operate in basically the same manner, the completion plug and flange are manufactured, so as to allow the flange, to accept and lock into place, a completion plug.
This completion plug is set below the valve, once set, pressure above the plug can be bled off, and the valve can then be removed.
Once the plug has been properly positioned, it is locked into place with the lock ring segments, this prevents plug movement, with the o-ring becoming the primary seal.
Several different types of completion plugs have been developed with metal to metal seals, in addition to the o-ring seal.
Line Stopping
Procedure
All following images are from Furmanite.
They are a little matched to the style
of this website requirements.
Line StopLine Stop
Line StopLine StopLine Stop
Line StopLine StopLine Stop
Line StopLine StopLine Stop
Line StopLine StopLine Stop
Line StopLine StopLine Stop

Source: http://www.wermac.org/specials/hottap.html accessed at 23rd Jan 2015 16.55 GMT +7

Pipeline Crack Propagation

Polyethylene (PE) is the primary material used for gas pipe applications. Because of its flexibility, ease of joining and long-term durability, along with lower installed cost and lack of corrosion, gas companies want to install PE pipe instead of steel pipe in larger diameters and higher pressures. As a result, rapid crack propagation (RCP) is becoming a more important property of PE materials.
This article reviews the two key ISO test methods that are used to determine RCP performance (full-scale test and small-scale steady state test), and compare the values obtained with various PE materials on a generic basis. It also reviews the status of RCP requirements in industry standards; such as ISO 4437, ASTM D 2513 and CSA B137.4. In addition, it reviews progress within CSA Z662 Clause 12 and the AGA Plastic Materials Committee to develop industry guidelines based on the values obtained in the RCP tests to design against an RCP incident.
Background
Although the phenomenon of RCP has been known and researched for several years 1, the number of RCP incidents has been very low. A few have occurred in the gas industry in North America, such as a 12-inch SDR 13.5 in the U.S. and a 6-inch SDR 11 in Canada, and a few more in Europe.
With gas engineers desiring to use PE pipe at higher operating pressures (up to 12 bar or 180 psig) and larger diameters (up to 30 inches), a key component of a PE piping material - resistance to rapid crack propagation (RCP) - becomes more important.
Most of the original research work conducted on RCP was for metal pipe. As plastic pipe became more prominent, researchers applied similar methodologies used for metal pipe on the newer plastic pipe materials, and particularly polyethylene (PE) pipe 2. Most of this research was done in Europe and through the ISO community.
Rapid crack propagation, as its name implies, is a very fast fracture. Crack speeds up to 600 ft/sec have been measured. These fast cracks can also travel long distances, even hundreds of feet. The DuPont Company had two RCP incidents with its high-density PE pipe, one that traveled about 300 feet and the other that traveled about 800 feet.
RCP cracks usually initiate at internal defects during an impact or impulse event. They generally occur in pressurized systems with enough stored energy to drive the crack faster than the energy is released. Based on several years of RCP research, whether an RCP failure occurs in PE pipe depends on several factors:
  1. Pipe size.
  2. Internal pressure.
  3. Temperature.
  4. PE material properties/resistance to RCP.
  5. Pipe processing.
Typical features of an RCP crack are a sinusoidal (wavy) crack path along the pipe, and “hackle” marks along the pipe crack surface that indicate the direction of the crack. At times, the crack will bifurcate (split) into two directions as it travels along the pipe.

Test Methods
The RCP test method that is considered to be the most reliable is the full-scale (FS) test method, as described in ISO 13478. This method requires at least 50 feet of plastic pipe for each test and another 50 feet of steel pipe for the reservoir. It is very expensive and time consuming. The cost to obtain the desired RCP information can be in the hundreds of thousands of dollars.
Due to the high cost for the FS RCP test, Dr. Pat Levers of Imperial College developed the small-scale steady state (S4) test method to correlate with the full-scale test3. This accelerated RCP test uses much smaller pipe samples (a few feet) and a series of baffles, and is described in ISO 13477. The cost of conducting this S4 testing is still expensive, but less than FS testing. Several laboratories now have S4 equipment. A photograph with this article shows the S4 apparatus used by Jana Laboratories.
Whether conducting FS or S4 RCP testing, there are two key results used by the piping industry; one is the critical pressure and the other is the critical temperature.
The critical pressure is obtained by conducting a series of FS or S4 tests at a constant temperature (generally 0C) and varying the internal pressure. At low pressures, where there is insufficient energy to drive the crack, the crack initiates and immediately arrests (stops). At higher pressures, the crack propagates (goes) to the end of the pipe. The critical pressure is shown by the red line in Figure 1 as the transition between arrest at low pressures and propagation at high pressures. In this case, the critical pressure is 10 bar (145 psig).
Figure 1: Critical Pressure (Plot of crack length vs. pressure)
Data obtained at 0° C (32°F).
Due to the baffles in the S4 test, the critical pressure obtained must be corrected to correlate with the FS critical pressure. There has been considerable research within the ISO community conducted in this area. Dr. Philippe Vanspeybroeck of Becetel chaired a working group - ISO/TC 138/SC 5/WG RCP - that conducted S4 and FS testing on several PE pipes 4. Based on their extensive research effort, the WG arrived at the following correlation formula 5 to convert the S4 critical pressure (Pc,S4) to the FS critical pressure (Pc,FS):
Pc,FS = 3.6 Pc,S4 + 2.6 bar (1)
It is important to note that this S4/FS correlation formula may not be applicable to other piping materials, such as PVC or polyamide (PA). For example, Arkema has conducted S4 and FS testing on PA-11 pipe and found a different correlation formula for PA-11 pipe 6.
The critical temperature is obtained by conducting a series of FS or S4 tests at a constant pressure (generally 5 bar or 75 psig) and varying the temperature 7. At high temperatures the crack initiates and immediately arrests. At low temperatures, the crack propagates to the end of the pipe. The critical temperature is shown by the red line in Figure 2 as the transition between arrest at high temperatures and propagation at low temperatures. In this case, the critical temperature is 35°F (2°C).
Figure 2: Critical Temperature (Plot of crack length vs. temperature)
Data obtained at 5 bar (75 psig).

RCP In ISO
The International Standards Organization (ISO) product standard for PE gas pipe, ISO 4437, has included an RCP requirement for many years 8. This is because there were some RCP failures in early generation European PE gas pipes, and the Europeans had conducted considerable research on RCP in PE pipes. Also, European gas companies were using large-diameter pipes and higher operating pressures for PE pipes, both of which make the pipe more susceptible to RCP failures. Below is the current requirement for RCP taken from ISO 4437:
Pc > 1.5 x MOP (2)
Where: Pc = full scale critical pressure, psig
MOP = maximum operating pressure, psig
Most manufacturers use the S4 test to meet this ISO 4437 RCP requirement. If the requirement is not met, then the manufacturer may use the FS test. Therefore, the ISO 4437 product standard requires that RCP testing be done, and also provides values for the RCP requirement.
RCP In ASTM
Until recently, ASTM D 2513 did not address RCP at all 9. The AGA Plastic Materials Committee (PMC) requested that an RCP requirement be added to ASTM D 2513, similar to the RCP requirement in the ISO PE gas pipe standard ISO 4437. The manufacturers agreed to include a requirement in ASTM D 2513 that RCP testing (FS or S4) must be performed. The ASTM product standard D 2513 does not include any required values.
PMC has agreed with this approach and will develop its own industry requirement in the form of a “white paper.” 10 The first draft was just issued within PMC with the following proposed requirement:
  1. PC,FS > leak test pressure.
  2. Leak test pressure = 1.5 X MOP.

RCP In CSA
CSA followed the direction of ASTM. The product standard CSA B137.4 11 requires that the RCP testing must be done. The values of the RCP test will be stipulated in CSA Z662 Clause 12, which is the Code of Practice for gas distribution in Canada. Clause 12 recently approved the requirement as shown nearby.
12.4.3.6 Rapid Crack Propagation (RCP) Requirements
When tested in accordance with B137.4 requirements for PE pipe and compounds, the standard PE pipe RCP Full-Scale critical pressure shall be at least 1.5 times the maximum operating pressure. If the RCP Small-Scale Steady State method is used, the RCP Full-Scale critical pressure shall be determined using the correlation formula in B137.4.
(end of box)

RCP Test Data
The critical pressure is the pressure - below which - RCP will not occur. The higher the critical pressure, the less likely the gas company will have an RCP event. In most cases, as the pipe diameter or wall thickness increases, the critical pressure decreases. Therefore, RCP is more of a concern with large-diameter or thick-walled pipe. Following are some typical critical pressure values for various generic PE materials. For most cases, the pipe size tested is 12-inch SDR 11 pipe.
PE Material S4 Critical Pressure (PC,S4) at 32°F (0°C)/Full Scale Critical Pressure (PC,FS) @ 0°C
Unimodal MDPE 1 bar (15 psig)/6.2 bar (90 psig)
Bimodal MDPE 10 bar (145 psig) /38.6 bar (560 psig)
Unimodal HDPE 2 bar (30 psig)/9.8 bar (140 psig)
Bimodal HDPE (PE 100+) 12 bar (180 psig)/45.8 bar (665 psig)
In general, the RCP resistance is greater for HDPE (high-density PE) than MDPE (medium-density PE). However, there is a significant difference when comparing a unimodal PE to a bimodal PE material, about a ten-fold difference.
Bimodal PE technology was developed in Asia and Europe in the 1980s. This technology is known to provide superior performance for both slow crack growth and RCP, as evidenced by the table. For the bimodal PE 100+ materials used in Europe and Asia, the S4 critical pressure minimum requirement is 10 bar (145 psig), which converts to 560 psig operating pressure. This means that with these bimodal PE 100+ materials, RCP will not be a concern. Today, there are several HDPE resin manufacturers that use this bimodal technology. Recently, a new bimodal MDPE material was introduced for the gas industry 12,13 with a significantly higher S4 critical pressure compared to unimodal MDPE - 10 bar compared to 1 bar.
Another measure of RCP resistance is the critical temperature. This is defined as the temperature above which RCP will not occur. Therefore, a gas engineer wants to use a PE material with a critical temperature as low as possible. Although critical temperature is not used as a requirement in the product standards, it is an important parameter, and perhaps should be given more consideration. Following is a table with some typical critical temperature values for various generic PE materials. For most cases, the pipe size tested is 12-inch SDR 11 pipe.
PE Material/Critical Temperature (TC) at 5 bar (75 psig)
Unimodal MDPE 15°C (60°F)
Bimodal MDPE -2°C (28°F)
Unimodal HDPE 9°C (48°F)
Bimodal HDPE -17°C (1°F)
Again, we see that RCP performance for HDPE is slightly better than MDPE, but there is a significant difference between bimodal PE and unimodal PE. The bimodal MDPE and HDPE materials have the lowest critical temperatures, which means the greatest resistance to RCP.

Conclusion
As gas companies use PE pipe in more demanding applications, such as larger pipe diameters and higher operating pressures, the resistance of the PE pipe to rapid crack propagation (RCP) becomes more important. In this article we have discussed the phenomenon of RCP and the two primary test methods used to determine RCP resistance - the S4 test and the Full Scale test. We reviewed the correlation formula between the FS test and S4 test for critical pressure. We have also discussed the two primary results of RCP testing - the critical pressure and the critical temperature.
ISO standards were the first to recognize the importance of RCP, especially in larger diameter pipe sizes, and incorporated RCP requirements in product standards, such as ISO 4437. The Canadian standards soon followed, and an RCP test requirement has been added to CSA B137.4. The required values for RCP testing are being added to the CSA Code of Practice in CSA Z662 Clause 12 for gas piping. ASTM just added an RCP requirement to its gas pipe standard ASTM D 2513. The corresponding AGA PMC project to develop RCP recommendations for required values from RCP testing is in progress.
In this article, we also discussed some results of RCP testing. In general, the HDPE materials have slightly greater RCP resistance than MDPE materials used in the gas industry. A more significant difference is observed when comparing unimodal PE materials to bimodal PE materials. Existing data indicate that bimodal HDPE materials show a significant increase in critical pressure compared to unimodal HDPE materials and also have considerably lower critical temperature values.
In addition, this bimodal technology has now just been introduced for MDPE. This bimodal MDPE material also has a significantly higher S4 critical pressure (10 bar vs. 1 bar) and a lower critical temperature than unimodal MDPE materials. With several PE resin manufacturers being able to produce bimodal PE materials, it is likely that in the near future, all PE materials used for the gas industry will be bimodal materials because of their superior RCP resistance.

Wednesday, January 21, 2015

Underwater Welding Career: What it is and how it is done

Are you wondering what it’s like to work as an underwater welder? Here’s a glimpse into what your underwater welding career might look like:
Where you might go
Take a typical oil rig. As an underwater welder, you would meet your dive team at the marina with your bags packed. Your team would get on a crew boat and travel several hours out to the oil rig. It’s important for you as an underwater welder to bring everything you need! Your job as an underwater welder on the rig might take several weeks or several months – and you might not return to the shore during that period of time.
What you might do
Once on the oil rig, your underwater welding career would have you participate in an overall inspection of the rig: What cross-members need to be repaired or replaced due to storm damage? What joints have suffered corrosion? Where has the structural integrity of the rig been compromised? Wet welding on the rig starts at the bottom and proceeds toward the top. Since everything on the rig is metal, all repairs and replacements require your expertise as an underwater welder.
Your underwater welding career would likely also include working in a hyperbaric habitat: essentially a large box that allows you as the underwater welder to have a dry environment in which to work. The hyperbaric habitat used on an underwater welding job can be so small there is just room enough for you to insert your hands and manipulate your welding tools, or so large that multiple underwater welders can climb in and work multiple welds simultaneously.
What you might earn
An underwater welding career can be lucrative. But what determines your underwater welding pay?
Underwater welding pay is ultimately based on three key aspects:
1. The underwater welder’s personal expertise. Underwater welding pay takes the individual very much into account. A fast, efficient, skilled underwater welder will receive a salary corresponding to his or her expertise. As a result, underwater welders’ salaries can increase rapidly as skill is demonstrated.
2. The geographic location of the company. Underwater welding pay in Louisiana, for instance, will typically be less than a comparable job would receive in New York. There are two reasons for this: first, underwater welders’ salaries may be influenced by union wages in one location and not in another. Second, the cost of living of the area usually influences salary levels across the board.
3. The type and size of the company. Small commercial diving firms may have 1-5 crews, medium companies may have 8-12 crews, and large businesses may have 20 or more crews on staff. As a general rule of thumb, the larger the company, the more they can afford to pay.
Given the above, you have a great deal of control over the underwater welding pay you receive in your underwater welding career!
Source: http://www.diversacademy.edu/content/underwater-welding-careers accessed at 21st Jan 2015, 20.59 GMT+7

Pig: What Is It?

While buildup in a pipeline can cause transmittal slows or even plugging of the pipeline, cracks or flaws in the line can be disastrous. A form of flow assurance for oil and gas pipelines and flowlines, pipeline pigging ensures the line is running smoothly.

The maintenance tool, pipeline pigs are introduced into the line via a pig trap, which includes a launcher and receiver. Without interrupting flow, the pig is then forced through it by product flow, or it can be towed by another device or cable. Usually cylindrical or spherical, pigs sweep the line by scraping the sides of the pipeline and pushing debris ahead. As the travel along the pipeline, there are a number functions the pig can perform, from clearing the line to inspecting the interior.

Engineers must consider a number of criteria when selecting the proper pig for a pipeline. First, it's important to define what task the pig will be performing. Also, size and operating conditions are important to regard. Finally, pipeline layout is integral to consider when choosing a pig.

Because every pipeline is different, there is not a set schedule for pigging a line, although the quantity of debris collected in a pipeline and the amount of wear and tear on it can increase the frequency of pigging. Today, pipeline pigging is used during all phases of the life of a pipeline.

Types Of Pipeline Pigs
Although first used simply to clear the line, the purpose of pipeline pigging has evolved with the development of technologies. Utility pigs are inserted into the pipeline to remove unwanted materials, such as wax, from the line. Inline inspection pigs can also be used to examine the pipeline from the inside, and specialty pigs are used to plug the line or isolate certain areas of the line. Lastly, gel pigs are a liquid chemical pigging system.
Debris after pigging
Debris after piggingSource: www.ppsa-online.com
Similar to cleaning your plumbing line,utility pigs are used to clean the pipeline of debris or seal the line. Debris can accumulate during construction, and the pipeline is pigged before production commences. Also, debris can build up on the pipeline, and the utility pig is used to scrape it away. Additionally, sealing pigs are used to remove liquids from the pipeline, as well as serve as an interface between two different products within a pipeline. Types of utility pigs include mandrel pigs, foam pigs, solid cast pigs and spherical pigs.
Inspection pigs, also referred to as in-line inspection pigs or smart pigs, gather information about the pipeline from within. . The type of information gathered by smart pigs includes the pipeline diameter, curvature, bends, temperature and pressure, as well as corrosion or metal loss. Inspection pigs utilize two methods to gather information about the interior condition of the pipeline: magnetic flux leakage (MFL) and ultrasonics (UT). MFL inspects the pipeline by sending magnetic flux into the walls of the pipe, detecting leakage, corrosion, or flaws in the pipeline. Ultrasonic inspection directly measures the thickness of the pipe wall by using ultrasonic sounds to measure the amount of time it takes an echo to return to the sensor
Specialty pigs, such as plugs, are used to isolate a section of the pipeline for maintenance work to be performed. The pig plug keeps the pipeline pressure in the line by stopping up the pipeline on either side of where the remedial work is being done.
A combination of gelled liquids, gel pigs can be used in conjunction with conventional pigs or by themselves. Pumped through the pipeline, there are a number of uses for gel pigs, including product separation, debris removal, hydrotesting, dewatering and condensate removal, as well as removing a stuck pig.
Because there now exist multi-diameter pipelines, dual and multi-diameter pigs have been developed, as well.

Source: https://www.rigzone.com/training/insight.asp?insight_id=310&c_id=19 accessed at 21st Jan 2015, 20.45 GMT+7